In Centerville the sewer is arriving street by street, so two similar homes a few blocks apart can be at different stages of the project.
Where the pipe is, and where it goes next
The Town is building in Centerville in phases, and on publish day each phase is at a different stage.
| Phase | Streets named by the Town | Status as published by the Town |
|---|---|---|
| Centerville North | North of Route 28 | Listed as active construction |
| Phinney's Lane Neighborhoods | Crosby Road, Pond Street, Lake Drive, part of Juniper Road, Brezner Lane, Tellegen Trail, Sail-A-Way | Scheduled to begin Nov. 2, 2026, with work on these roads planned between November 2026 and January 2027 |
| Centerville South | Old Stage Road from Route 28 to Main Street; Main Street from Old Stage Road to South Main Street; Craigville Beach Road from South Main Street to the Centerville River Bridge; Old Post Road from Old Stage Road to Phinney's Lane; Park Avenue from Bacon Lane to Main Street; Bacon Lane, Maple Avenue and Linden Avenue | Construction anticipated to begin in early 2027 |
The South phase includes part of Main Street, the same street where the Centerville Civic Association holds its Christmas Stroll on Dec. 6, 2026, from 4 to 6 p.m. The Town has scheduled an in-person information meeting on the South phase for Wednesday, Nov. 18, 2026, at 6 p.m. at the Barnstable Adult Community Center, 825 Falmouth Road in Hyannis. The Town says the meeting will be recorded and posted at BarnstableWaterResources.com.
For a home listed on Linden Avenue or Craigville Beach Road this winter, a sewer that is coming but isn't live yet affects the transaction.
Four costs of connecting to sewer
Barnstable's Homeowner's Sewer Connection Guide, Fall 2025 edition, lists what an owner connecting to new sewer pays.
- The Sewer Assessment. This is a one-time charge, currently capped at $10,000 per sewer unit. It is calculated as the lesser of that cap or the property's share of the infrastructure cost. A residential unit is one dwelling unit.
- The private connection. The owner hires a licensed sewer installer to run the line from the house to the Town's stub in the street and to abandon the existing septic system. The Town says the price depends on the property and comes from the installer's quote. As of June 30, 2025, the connection permit for a single-family home was $420, with $300 more if a pump station is needed.
- A grinder pump, if gravity won't work. The Town buys the first pump and the installer puts it in. After that the owner owns it and pays for maintenance and any replacement.
- The utility bill. Sewer charges are based on water use and are billed on the same schedule as the water bill. An irrigation deduct meter can lower the charge for water that never goes into the sewer. The Town's sewer connection one-sheet puts the typical residential bill at about $490 a year.
The Town's FY2025 annual report says Barnstable issued its first sewer assessments in August 2024, for Strawberry Hill Road.
Paying the assessment
An owner can pay the assessment in full or spread it over up to 30 years in quarterly installments on the property tax bill. According to the Town's financial resources page, the interest rate is two percentage points above the Town's borrowing rate unless Town Council sets a different rate. Choosing installments records a lien at the Registry of Deeds.
Help with the bill
The Massachusetts Department of Revenue's residential property tax credits page, updated March 10, 2026, describes the Title 5 credit, with a maximum credit of $18,000 for eligible costs.
The Town's financial resources page lists AquiFund loans at 0%, 2%, 4% or 5%. The page also lists sewer and water connection loans from Cape Cod Five, and personal loans of $5,000 to $25,000 from Cape & Coast Bank.
This post is general information, not legal, tax or financial advice. Please confirm your own situation with the Town, the Board of Health, your attorney and your tax advisor before you act.
Frequently Asked Questions
Does my Centerville street have a construction date yet? For the Phinney's Lane Neighborhoods roads, the Town has published a November 2026 to January 2027 work window. For the South phase streets, including Main Street and Craigville Beach Road, the Town expects construction to begin in early 2027. Questions can go to Christopher Gadd at the Department of Public Works, 508-790-6400.
Who answers assessment questions? The Barnstable Treasurer/Collector's Office, at 508-862-4054.
If you own a home on one of these Centerville streets and are thinking about selling, Colleen Riley and Sabrina can go through where your street stands and how that affects pricing and negotiation, starting with a free home valuation. You can also find more about the village on our Centerville page.